AVL Technology Centre Coventry

Updated: Dec 9, 2019


Nestled within the Coventry business park AVL Technology Centre required extensive groundwork and civil work to establish roads and footing for the steel construction building.

The AVL building was to be used as a testing facility for Jaguar Land/Rover.

As part of this project Hawkes Group was responsible:

Mass Pour Foundations

Bolt Sets

Earthworks cut and fill

Enabling works for road

Car Park and service yard including Kerbs

In situe RC structure

Hard Landscaping importing top soil

Finishing work

Swale construction























Hawkes Civil Engineering teams on site with excavators, tippers, rollers and dumpers from our own huge range of plant and equipment.

21 views0 comments

Recent Posts